High School Synthetic Turf
- October 21, 2010 – (see images and description below)
Work completed to date:
- Temporary access road and bridge installed
- Existing topsoil removed
- New sub-base installed, compacted and tested
- Installation of perimeter drainage completed
- Three (3) electrical conduit lines for future use installed
- Elevate all catch basins and tie-in/complete drainage
- Establishment of subgrade
- Paving of the asphalt D-area behind the North endzone
- Geotextile fabric and flat panel drains installed on top of subgrade
- Import and establish grade of stone base
- The field turf panels have been fully installed
- Sewing of inlaid sports lines and yard marker numbers has begun
- Asphalt rubber surfacing of D-area and perimeter trench drain is complete
- Painting of "CLIPPER PRIDE" in the rubber/asphalt D-area complete